This project will make the Greathall sparkle again. We like to have this done well ahead of camp as many potential campers come to tour the site in the spring. A tidy site provides confidence in our operation
Skills: Mostly domestic engineering. ( dusting, mopping, organising, carpet cleaning, etc.) Some carpentry for phase 3
Tools: You guessed it, mops, brooms, webster, rug shampooer.
Phase 1: 3rd floor
Team: 4 detail oriented folks that hate dirt and clutter
- Finish redecorating the Music Cafe
- Move furniture and shampoo carpet
- Dust beams
- Cobweb patrol
- Organize shelfs
Phase 2: Main floor
Team: 4 detail oriented folks that hate dirt and clutter, 2 painters
- Wash windows
- Put up summer curtains
- Touch up floor paint
- Organize entry
Phase 3: Basement
Team: 4 detail oriented folks that hate dirt and clutter, 2 painters, 2 Carpenters
- Wash windows
- Replace curtains with blinds
- Finish Benches
- Organize program supplies
- Organize infirmary/Nurses office